E-115 115kV Line
2022: Eversource Transmission Cost Allocation application
2017 river crossings, no mention of pole degradation
December 2021, petition attachment, 12/2016 original date, pole heights 52'-106'
October 2022 PAC presentation, local system plan
March 2023 request to NEPOOL for TCA