B-112 115kV line
2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024
May 18, 2023 Line rebuild presentation to PAC
fact sheet
2023, May 17: Dear Neighbor letter about reliable power
2022 application
2022 application exhibits
2022 staff recommendation
2022 license
Undated NHEC response to stakeholder comments on nh 2029 solutions study update