B-112 115kV line
2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024
2022 application
2022 application exhibits
2022 staff recommendation
2022 license
May 18, 2023 Line rebuild presentation to PAC
fact sheet
May 2023 Dear Neighbor letter about reliable power
Undated NHEC response to stakeholder comments on nh 2029 solutions study update