B-112 115kV line
2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024
May 18, 2023 Line rebuild presentation to PAC
fact sheet
2023, May 17: Dear Neighbor letter about reliable power
2023, March 31: DES permission with waivers
2023, March 31, cover letter for final documents transmittal
2023, February 3: NH Fish & Game's "recommended permit conditions that were initially issued 11/18/22 amended to include the unavoidable vernal pool buffer impacts"
2022 application
2022 application exhibits
2022 staff recommendation
2022, November 18" license
Undated NHEC response to stakeholder comments on nh 2029 solutions study update