R-193 115kV line
2023, June 27: Alteration of Terrain permit with waivers
2023, June 16: Alteration of Terrain plans
2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "
2023, May 18, presentation to PAC, replace 30 out of 177 structures; $7.7 million
2023 may 18 PAC minutes
2023, May 5: cover letter for Alteration of Terrain application. "The proposed project includes the replacement of 76 existing utility structures on the R193, A126, and H141 transmission lines that must be replaced because they have reached the end of their service life."
2018, October 17, presentation to PAC, replace 49 structures, $8.3 million