This is an old revision of the document!
H-141 115kV line
2018 PAC submission
petition
2023 crossing application
2023 exhibits
2023 staff recommendation
2023 license
2023 license revision memo
2023 revised license
notice of decision ES
2021 crossing order of notice
ES permit by notification
2021 crossing recommendation
September 2021, intra-department communication
h-141_2023.pdf
October 2018 PAC presentation
2023 Danville Planning Board: "The structure replacements were selected based on site visit evaluations conducted by Eversource and must be replaced for the transmission line to continue to function safely and reliably."
May 2019 Exeter Conservation Commission meeting packet
October 2021 Brentwood planning board minutes
recommendation