391 345kV Line
2023, May 18, presentation to PAC, replace 39 out of 335 structures; $12.4 million
2022, August 19; Alteration of Terrain DES approval and waiver letter 391, 373, 385
2022, June 15 presentation to PAC, rreplace 27 out of 345 poles; $9. million
2022, May; Alteration of Terrain drawings, 391, 373, 385
2017, December presentation to PAC, replacement of 69 out of 335 poles; $19.6 million
delineated wetland under 391, "upgrade"
delineated wetland under 391, wetlands are not an asset, 'for' Eversource.
delineated wetland under 391, "upgrade"
2020, January 20; Surface and Groundwater overlay plans
aot-1781_start_of_construction.pdf
aot-1781_start_of_construction.pdf
2020, April 3; DES permission to Alter the Terrain, with waivers
2019, July 1 Start of Construction form
2019, June 28; DES permission to Alter Terrain, with waivers, 391, 373, 385
2019, May; Alteration of Terrain permit application
2019, April 24; Alteration of Terrain plans for structure replacements 391, 373, 385