B-143 115kV line

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, replace 46 out of 154 structures and reconductor with Optical Ground Wire (OPGW); $17.3 million

map showing line location

19-146_2019-09-04_eversource_petition_crossing_baboosic.pdf

19-146_2019-11-07_staff_recommendation.pdf

December 2019, 2020-2023 revisions PAC presentation

Same as above but "clean"

b143_map_and_drawings.pdf