391 345kV Line

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, replace 39 out of 335 structures; $12.4 million

2022, August 19; Alteration of Terrain DES approval and waiver letter 391, 373, 385

2022, June 15 presentation to PAC, replace 27 out of 345 poles; $9. million for 391 line

2022, June 1; Alteration of Terrain application 391 line.

2022, April, Alteration of Terrain Plans, 391, 373, 385

2022, May; Alteration of Terrain drawings, 391, 373, 385

map showing line location

delineated wetland under 391, "upgrade"

delineated wetland under 391, wetlands are not an asset, 'for' Eversource.

delineated wetland under 391, "upgrade"

2020, January 20; Surface and Groundwater overlay plans

2020: Start of Construction form

2020, April 3; DES permission to Alter the Terrain, with waivers

2019, July 1 Start of Construction form

2019, June 28; DES permission to Alter Terrain, with waivers, 391, 373, 385

2019, May; Alteration of Terrain permit application

2019, April 24; Alteration of Terrain plans for structure replacements 391, 373, 385

2017, December presentation to PAC, replacement of 69 out of 335 poles; $19.6 million