373 345kV Line

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, replace 34 out of 178 structures; $10.3 million

2022, June 15 report to PAC, replace 25 out of 169 structures; $8.6 m

2021 presentation to PAC, 22 structures out of 178 replaced, $9.8 m

2018 article on maintenance work, not described

2020, September 23, Deerfield Plann{{ :373:aot-1632_start_of_construction.pdf |aot-1632_miscellaneous_r.pdfing Board minutes}}

2020,

Alteration of Terrain

Alteration of Terrain

Alteration of Terrain

de-20-195-order-26-468.pdf