307 345kV line

2023, May 23: DES permission for alteration of terrain with waivers

2023, Fish & Game restrictions on work

2022, June 16: e-mail with restrictions on work

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, Replace 15 out of 46 structures and reconductor with Optical Ground Wire (OPGW); $9.4 million

map showing line location

2023, March 23: Oyster River Local Advisory Committee comments

Fish & Game permit conditions

2023, February 8: alteration of terrain application

2023, March 7: Eversource application for river crossing

2-cre-2023-005_exhibits_1_to_5.pdf

3-cre-2023-005-energy-staff-recommendation.pdf

4-cre-2023-005-license.pdf

326_ras_retirement_project_i_3_9_letter_es_22_x01.pdf

2022, June 15, presentation to PAC

2019, February 11, submission to NEPOOL

durham_permitted_use_app_final_11.26.2019.pdf

planners_review.pdf

2017, December presentation to PAC, replacement of 47 out of 145 poles.

2017, December 17, Deerfield Conservation Commission minutes

wetland under the 307, southeast of the deerfield ss

wetland under the 307

tops and debris in wetland under the 307