u-199 [2023/08/15 16:02] sigridundset |
u-199 [2023/08/15 16:03] (current) sigridundset |
{{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} | {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} |
| |
{{ ::b112-u199-q195_rebuild_presentation.pdf |Line rebuild presentation}} | {{ ::b112-u199-q195_rebuild_presentation.pdf |2023, May 18, presentation to PAC}} |
| |
| |