 U-199 115kV line U-199 115kV line
  
-{{ ::b112-u199-q195_rebuild_presentation.pdf |Line rebuild presentation}}+{{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} 
 + 
 +{{ ::b112-u199-q195_rebuild_presentation.pdf |2023, May 18, presentation to PAC}} 
 + 