This shows you the differences between two versions of the page.
| Next revision | Previous revision | ||
|
t-198 [2023/06/14 17:02] sigridundset created |
t-198 [2023/08/15 14:05] (current) sigridundset |
||
|---|---|---|---|
| Line 1: | Line 1: | ||
| T-198 115kV line | T-198 115kV line | ||
| - | {{ :: | + | {{ :: |
| - | {{ : | + | {{ : |
| - | {{ ::license-granted_t-198.pdf |}} | + | {{ ::a4_eversource_115kv_and_345kv_structure_replacements.pdf |2021 presentation to PAC, 64 out of 154 structures replaced, $19.1 m.}} |
| - | {{ ::petition_t-198.pdf |}} | + | {{ ::license-granted_t-198.pdf |order}} |
| - | {{ ::t-198.pdf |}} | + | {{ ::petition_t-198.pdf |petition}} |
| - | {{ :: | + | {{ ::t-198.pdf |December 2021: Inter-departmental communication}} |
| + | |||
| + | {{ :: | ||