T-198 115kV line | T-198 115kV line | ||
- | {{ :: | + | {{ :: |
- | {{ : | + | {{ : |
- | {{ ::license-granted_t-198.pdf |}} | + | {{ ::a4_eversource_115kv_and_345kv_structure_replacements.pdf |2021 presentation to PAC, 64 out of 154 structures replaced, $19.1 m.}} |
- | {{ ::petition_t-198.pdf |}} | + | {{ ::license-granted_t-198.pdf |order}} |
- | {{ ::t-198.pdf |}} | + | {{ ::petition_t-198.pdf |petition}} |
- | {{ :: | + | {{ ::t-198.pdf |December 2021: Inter-departmental communication}} |
+ | |||
+ | {{ :: |