 B-112 115kV line B-112 115kV line
 +
 +
  
 {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024}} {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024}}