User Tools

Site Tools


b-112

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
b-112 [2023/08/26 09:39]
sigridundset
b-112 [2023/08/30 11:50] (current)
sigridundset
Line 1: Line 1:
 B-112 115kV line B-112 115kV line
 +
 +
  
 {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024}} {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 254 wood structures with new steel structures, Re-conductor 22.9 miles of 336 ACSR with 1272 ACSS, Install 45.8 miles of OPGW (2 x 22.9 mi) Estimated PTF Cost: $105.43M (-25% / +50%) Projected In-service Date: Q4, 2024}}
Line 21: Line 23:
 {{ ::3_-cre-2022-023-energy-staff-recommendation.pdf |2022 staff recommendation}} {{ ::3_-cre-2022-023-energy-staff-recommendation.pdf |2022 staff recommendation}}
  
-{{ ::4_-_cre-2022-023-license.pdf |2022 license}}+{{ ::4_-_cre-2022-023-license.pdf |2022, November 18" license}}
  
 {{ ::responses_to_stakeholder_comments_on_the_new_hampshire_2029_solutions_study_update.pdf |Undated NHEC response to stakeholder comments on nh 2029 solutions study update}} {{ ::responses_to_stakeholder_comments_on_the_new_hampshire_2029_solutions_study_update.pdf |Undated NHEC response to stakeholder comments on nh 2029 solutions study update}}
b-112.1693039158.txt.gz ยท Last modified: 2023/08/26 09:39 by sigridundset