Line 2: Line 2:
  
  
-{{ ::e_22018-9_115kv_pac_submissions.pdf |2018 PAC submission, replace 29 structures}} 
  
-{{ ::a2_eversource_laminated_wood_structure_replacements_phase_2_rev1_redline.pdf |October 2021 PAC submission, laminated wood phase 2 revision 1}} 
  
-{{ ::a5_115kv_structure_replacement_and_asset_conditions_multiple_lines.pdf |October 2018 PAC presentation}}+{{ ::a152:aot2120_rm.pdf |2022, March 28, DES permission to alter terrain, with waivers}} 
 + 
 +{{ :a152:aot_stamped-2.pdf |2022, February 8: Stamped Alteration of Terrain plans}} 
 + 
 +{{ ::license-granted_a152.pdf |January 2022, license granted}} 
 + 
 +{{ :391:aot-2120_plans.pdf |2022,January; Structure replacement and OPGW Alteration of Terrain and Groundwater Overlay Plans}} 
 + 
 +{{ ::a2_eversource_laminated_wood_structure_replacements_phase_2_rev1_redline.pdf |October 2021 PAC submission, laminated wood phase 2 revision 1 replace 72 out of 242 structures at $15.3 m.}}
  
 {{ ::cr-2021-019-a152line-oon.pdf |2021 petition, following 2008 and 2019 petitions}} {{ ::cr-2021-019-a152line-oon.pdf |2021 petition, following 2008 and 2019 petitions}}
 +
 +{{ ::staff_recommendation.pdf |December 2021 staff recommendation,steel poles 65'-79'}}
  
 {{ ::crossing_petition.pdf |November 2021 crossing petition, wood to steel}} {{ ::crossing_petition.pdf |November 2021 crossing petition, wood to steel}}
  
-{{ ::de-19-157.pdf |September 2020 order granting crossings}}+{{ ::november_15_21_packet_0.pdf |November 2021  Keene Conservation Commission}}
  
 {{ ::exhibits_1_to_17.pdf |September 2021 exhibits dated December 2016}} {{ ::exhibits_1_to_17.pdf |September 2021 exhibits dated December 2016}}
  
-{{ ::november_15_21_packet_0.pdf |November 2021  Keene Conservation Commission}}+{{ ::de-19-157.pdf |September 2020 order granting crossings}}
  
-{{ ::staff_recommendation.pdf |December 2021 staff recommendation,steel poles 65'-79'}} +{{ ::e_22018-9_115kv_pac_submissions.pdf |2018October 17; PAC submission, replace 29 structures at $6.1. million}}
- +
-{{ ::license-granted_a152.pdf |January 2022, license granted}}+