 +====== A-111 115kV transmission line ======
 +
 +
 +
 {{ ::a05_1_es-21-tca-44_final.pdf |Application to ISO for TCA. Rebuilding line at the same size is not presented as an alternative. No pole inspections submitted. Described as reliability and asset condition project}} {{ ::a05_1_es-21-tca-44_final.pdf |Application to ISO for TCA. Rebuilding line at the same size is not presented as an alternative. No pole inspections submitted. Described as reliability and asset condition project}}
 +
 +{{ ::new_hampton_sb_minutes_3-3-22.png?linkonly |March 3, 2022 New Hampton Selectboard minutes. E$ wants work to be allowed 7 days a week, 7:00 am to 7:00 pm. Dump trucks are delivering gravel for road building and there will be drilling.}}
  
 {{ ::a5_webster_beebe_river_115kv_corridor_asset-conditions_and_opgw_project_lines_a111_e115_z180_rev1_clean.pdf |December 2020 Asset Condition PAC presentation}} {{ ::a5_webster_beebe_river_115kv_corridor_asset-conditions_and_opgw_project_lines_a111_e115_z180_rev1_clean.pdf |December 2020 Asset Condition PAC presentation}}
Line 5: Line 11:
 {{ ::a111-project-construction-factsheet.pdf |Project construction fact sheet citing reliability}} {{ ::a111-project-construction-factsheet.pdf |Project construction fact sheet citing reliability}}
  
-{{ ::2017_river_crossings_existing_poles_and_wires_just_fine.pdf |2017 river crossings, no mention of pole degradation}}+{{ ::e-115_and_a-111_2-15.png?linkonly |2015: "The load and added local generation in this area has not required the upgrading of either line."}}
  
-{{ ::a05_1_es-21-tca-44_final.pdf |Final TCA, $33. m.}} +{{ ::a05_1_es-21-tca-44_final.pdf |2021, August 19; Final TCA, $33. m.}}
- +
-{{ ::a05_1_es-23-tca-01_final.pdf |Final TCA Z-180}}+
  
 {{ ::a5_webster_beebe_river_115kv_corridor_asset-conditions_and_opgw_project_lines_a111_e115_z180_rev1_clean.pdf |October 2019 PAC presentation. A-111 listed as Asset Condition, not reliability project.}} {{ ::a5_webster_beebe_river_115kv_corridor_asset-conditions_and_opgw_project_lines_a111_e115_z180_rev1_clean.pdf |October 2019 PAC presentation. A-111 listed as Asset Condition, not reliability project.}}
Line 31: Line 35:
 {{ ::license-granted.pdf |January 2022, license granted}} {{ ::license-granted.pdf |January 2022, license granted}}
  
 +{{ ::staff_recommend.pdf |December 2021, staff recommendation}}
  
 +{{ ::2017_river_crossings_existing_poles_and_wires_just_fine.pdf |2017 river crossings, no mention of pole degradation}}
  
-{{ ::staff_recommend.pdf |staff recommendation}} 
  
-{{ ::staff-recommendation.pdf |staff recommendation}} 